New Mtentu Bridge contract under adjudication by Sanral

14-09-2021
Read : 799 times
Moneyweb
Source
The new tender for the construction of the Mtentu Bridge on the Wild Coast is under adjudication while litigation remains a possibility to resolve a dispute between the original contractor, the Aveng-Strabag Joint Venture (ASJV), and the South African National Roads Agency (Sanral).
Sanral N2 Wild Coast Road lead project manager Craig McLachlan said the new tender has not yet been awarded but Sanral anticipates appointing a new contractor before the end of 2021.
McLachlan added that the estimated contract duration is 49 months and the project value will be announced when the contractor has been appointed.
However, McLachlan said the scope of the new Mtentu Bridge contract includes additional work that was not included in the original ASJV contract.
Construction on the project by the ASJV ground to a halt in 2019.
JSE-listed construction and engineering group Aveng claimed at the time the ASJV had lawfully terminated the R1.5 billion contract following a force majeure event after civil unrest, commotion, protests and threats of harm had resulted in the joint venture being denied access to the site and the ability to safely continue the execution of the project.
However, Sanral CEO Skhumbuzo Macozoma claimed the ASJV abandoned the contract.
Aveng’s then wholly owned southern African construction and engineering business Grinaker-LTA was a 50% partner in the ASJV, but it subsequently sold Grinaker-LTA to the black-owned Laula Consortium in December 2019 for R72 million.
Litigation
McLachlan said Sanral and the ASJV have concluded two separate litigation processes to date related to Sanral’s right to call in the performance and retention guarantees.
He said the courts found in Sanral’s favour in both cases, as well as in an urgent application Sanral was required to bring shortly after the contract termination to prevent the ASJV from removing plant and equipment being held on site as additional surety.
McLachlan said Sanral will be in a position to conclude and submit its claim against the ASJV once a new contractor has been appointed for the Mtentu Bridge project.
“As per the FIDIC [International Federation of Consulting Engineers or Federation Internationale des Ingenieurs-Conseil] contract in place, this claim will be assessed by the engineer for the project.
“Should either party contest the resulting determination, there are various routes that may be followed, including referral to the project’s three-[person] Dispute Adjudication Body or alternatively arbitration or court action.
“This is still to be determined by the parties,” he said.
McLachlan added that Sanral has called in and been paid both the performance and retention sureties held, totalling about R270.9 million, to offset the potential additional costs to be incurred by the taxpayer due to the termination of the contract with ASJV.
He said these monies received will be offset against Sanral’s claim against the ASJV.
‘Conversation’ to be had
Aveng Group CEO Sean Flanagan said during a recent presentation on the group’s financial results in the year to June 2021 that Aveng assumes there will be some conversation between the group and Sanral on how they resolve their outstanding disputes once the new contractor has been awarded.
“Clearly we believe that we had the right to terminate our contract and that remains our position. But of course Sanral has a completely opposite view,” said Flanagan.
“Where there is an opportunity for us to sit down and find a resolution, we would do so but we would not do so by putting Aveng at risk.
“So unfortunately those matters will play out over a period of time, and what could be quite an extended period of time,” he said.
McLachlan said there currently aren’t any settlement negotiations underway between Sanral and the ASJV, nor any litigation currently pending.
Aveng group financial officer Adrian Macartney confirmed during Aveng’s recent results presentation that the group has recognised the cost of bonds being pulled relating to both the Mtentu Bridge project and The Leonardo contract in Sandon.
“We continue to face litigation there,” he added.
The Leonardo
The reference to The Leonardo relates to a notice sent to Aveng in January 2020 by Seventy Five on Maude, which is part of Bart Dorrestein’s Legacy Group, terminating that construction contract.
The Legacy Group also made a call on the R87.4 million construction guarantee procured by Aveng as part of that contract.
Flanagan reiterated that it is always Aveng’s preference to resolve disputes on contracts amicably and without having to resort to litigation.
“Unfortunately, in order to do that, you need two parties who are prepared to engage in a settlement negotiation.
“In the case of [The] Leonardo, that is not the case and so we have a number of disputes which are following their call offs through the contract, which in the first instance is arbitration.
“A number of those matters are either in the process of being heard or laid down to be heard in the coming months. But I think it’s some way off before we have resolution of those issues,” he said.
Eskom
Flanagan added that the major dispute Aveng had with Eskom was settled in the past year.
This dispute related to the non-payment by Eskom of amounts owing for the Majuba rail project in Mpumalanga.
Aveng confirmed in April 2020 it had in 2019 instituted a R40 million high court claim against the power utility because of non-payment on this contract.
Acting South Gauteng High Court Acting Judge JJ Reyneke in September 2020 ordered Eskom to pay Aveng R40.08 million.
Moving forward
Flanagan said last month Aveng management sees the year to end-June 2021 “as a very, very significant step forward in our road towards returning Aveng to the status it used to hold”.
Aveng reported headline earnings per share of R751 million compared to the R950 million loss in the previous year.
This was achieved on the back of a 23% rise in revenue to R25.7 billion from R20.9 billion.
Aveng also reported that it plans to undertake a share consolidation before the end of this year to reduce the more than 60 billion Aveng shares in issue.
The increase in the shares in issue follows several rights issues by the group to repair its balance sheet as part of the strategy to return the group to profitability.
Recent News
Here are recent news articles from the Building and Construction Industry.
Have you signed up for your free copy yet?