Brixton reservoir and tower project shows progress as it comes online
Advertising
03-02-2026
Read : 9 times
Northcliff Melville Times
Source
Johannesburg Water is advancing critical upgrades to stabilise supply in Brixton. The new Brixton reservoir and tower is online, supplying water while undergoing monitoring
With the new year well underway, a project that saw R800m injected to improve water quality for residents is now seeing better days, amid constant delays and frustration from residents.
Formal commission phase approaching soon
On January 27, Ward 87 councillor Kyle Jacobs conducted an oversight at the new Brixton reservoir and tower, confirming that it is now online and ready to supply water to the system, with monitoring and testing ongoing, according to the project manager.
Jacobs explained that the water utility brought the reservoir into operation in mid-January. “They did experience some issues initially, consisting of bursts and leaks on the supply lines, which required repairs and reconfiguration. However, that work has been completed, and the reservoir is now supplying water without further problems.”
Jacobs noted that residents connected to the reservoir will be closely monitored for any fluctuations in water pressure or supply issues. Johannesburg Water (JW) stated that they will liaise with residents to gather feedback, which will inform adjustments to the system as needed. “Even though the reservoir has been commissioned, it is still being monitored. Some streets may need adjustments to ensure all residents receive adequate supply. The network may require valve changes or reconfigurations as we learn how the systems behaves.”
JW spokesperson Nombuso Shabalala confirmed that the new structure has successfully passed all required construction and safety tests. “In addition, comprehensive water quality testing has been completed and approved by an accredited laboratory, confirming that the reservoir is safe for water storage and distribution. The outlet from the new reservoir was opened on January 16, marking a key milestone in the project.”
Shabalala added that the commissioning process is currently underway over the next few weeks. During this phase, she explains, minor technical issues were identified and are being addressed, with all outstanding work expected to be completed shortly. “At present, the reservoir is partially supplying the system, via a 200mm pipeline. Full operation of the system is anticipated to commence during the week commencing on January 26, subject to the successful completion of final checks.”
She explained that the structure has passed its water-tightness test, which involved filling the tower with water over several weeks to confirm the absence of leaks. “All pump station equipment associated with the tower has also successfully met testing requirements. The final tie-ins are scheduled in January, after which the formal commissioning phase will begin from February 3. This phase involves the gradual introduction of water into the system, close performance monitoring, and verification that all telemetry and control systems communicate effectively with JW’s central operations.”
Crosby pump station upgrade set for February changeover
Forming part of intervention to improve water supply reliability to the Brixton area, Ward 87 councillor Kyle Jacobs conducted an oversight at the Crosby pump station to report on the progress. He said the pump station is progressing, with a planned changeover to new temporary pumps also scheduled for February 3. He explained that the project manager confirmed fittings are currently being installed, and pipes connecting the pump station to Brixton have been laid. “They have installed the new pumps and are planning to switch from old pumps to these temporary pumps around February 3. This process will involve shutting off the current system, fitting the new pumps and bringing them online, which is expected to take about 36 hours.”
Shabalala said the existing pumps are ageing and are no longer able to consistently meet current demand. “To ensure that upgrades can be implemented without interrupting water supply, a temporary pump station has been installed. This temporary facility allows for the replacement of old equipment with new, higher capacity pumps.”
Once the upgrades are completed, she says the temporary pump station will remain in place as a backup facility, strengthening overall system resilience in the event of future failures. “Commissioning of the upgraded Crosby pump station is also planned to commence on February 3. Once fully operational, the Brixton reservoir and tower will increase water storage capacity in the area. This will improve supply stability and could reduce the risk of outages during interruptions from bulk supply.”
The Crosby pump station upgrades will further enhance the system’s ability to pump sufficient water into the network, particularly during peak demand periods, ensuring reliable service to customers. Shabalala ensured that updates will continue to be provided as the phase of testing and commissioning progresses. “Please note that this is not an event, but a process which will be implemented over the next few weeks.”
Jacobs stressed that water infrastructure projects, like the Cosby pump station, should be a priority. “These projects are essential for residents’ dignity and quality of life. The city must get its finances in order so work can continue and be completed on time.” He added that pressure will continue to be applied to ensure contractors are paid and that the pump station can provide sustainable, regular water supply to residents.
Recent News
Here are recent news articles from the Building and Construction Industry.
Have you signed up for your free copy yet?