Construction and operation of grid connection infrastructure consisting of a single circuit 132kV power line between the existing Emil Traction Substation and the authorised Olifantshoek Substation located near the town of Olifantshoek located within the Gamagara Local Municipality and the greater John
Aquila's Avontuur project area is located in the Northern Cape Province of South Africa near the towns of Kathu and Hotazel. Kathu is approximately 520 kilometres south-west of Johannesburg and Hotazel 68 kilometres north of Kathu. On both targets, Aquila has intersected significant zones of manganese
De Beers Consolidated Mines Limited has applied for a Prospecting Right on the Farm New Kingston in the Northern Cape. The area is approximately 130,4857 hectares in size. Application for the Prospecting Right was complied and submitted to the DMR. Prospecting for kimberlite is a dynamic and result-driven
Construction of the 240MW Mooi Plaats Solar PV Plant, and 132kV overhead power lines with associated grid connection, in the Umsobomvu Local Municipality, Pixley ka Seme District Municipality, Northern Cape. The generation capacity of the solar PV facility and the layout of the PV arrays will be dependent
Upgrades, additions and Routine Road Maintenance of National Route 10 Sections 5 to 8 between Kopieskraal (km 31.322) and Omdraai Vlei (km 61.641) situated in the Pixley Ka Seme District Municipality, Northern Cape. The project value is R 107 661 724.40. The exact GPS location is not known and the marker
Periodic Maintenance on the National Route 10 Section 5 from Ludlow at km 0.0 to Leuwekop at km 20.0 in the Northern Cape. R75 463 281.32. The GPS co-ordinates have been placed along the proposed construction route at 31°17'18.1"S 24°50'47.9"E
The proposed Sishen Expansion Project at SIOM comprises of further pit expansions that include Far south pushback 21 and 19, Lylyveld pit expansion, C&G stockpile at Far south and Lylyveld pit, Moolmans workshop, access road and pollution control dam, proposed Far south Waste Rock Dump,heavy and light
Periodic maintenance on the National Route 10 Section 5 from Leuwekop at km 20.00 to Luipertskop at km 40.00 in the Northern Cape. R69 873 408.03. The GPS co-ordinates have been placed along the proposed construction area on the N10 31°15'28.9"S 24°45'09.7"E
Construction of the proposed Phezukomoya 315MW wind energy facility and the associated infrastructure which will be located approximately eight kilometres south east of the town of Noupoort in the Northern Cape Province. Reippp 5. The exact co-ordinates are currently not available however the possible
Lehating Mining proposes to establish a new manganese mining operation near Hotazel in the Northern Cape. The project will involve underground mining accessed via a decline shaft, crushing, screening and transport of manganese ore as well as associated infrastructure and services. The mining and related