Construction of a mega bridge called Mtentu in total length of approximately 1 130m and comprises a main span of 260m constructed as a balanced cantilever with main piers approximately 160m high, plus approach viaducts constructed using incremental launching methods located in the Eastern Cape as part
Construction of Mgomanzi Senior Primary School located in Mbizana, Eastern Cape. The project value is R 54 454 716,74 The exact co-ordinates are 30°56'02.0"S 29°50'56.8"E.
Refurbishment, alterations and additions at Corridor 2A (Cluster 5) at the existing Isando Station and Tembisa Station in Pretoria Road, Kempton Park, Gauteng. The value of the project is R29 729 530,00. The scope of work will include, but not be limited to the following: removal and disposal of dilapidated
Construction and replacement of the existing water main in Mimosa Street, Jeffrey’s Bay, Eastern Cape. The project value is R 17 934 862,94. The scope of works could include: the construction of the new 315mm diameter uPVC water main in Mimosa Street starting in Noorsekloof road where it will connect
Refurbishment from level 7 to level 32 of the existing South African Reserve Bank Head Office Tower Block situated at 384 Helen Joseph Street, Pretoria, Gauteng. The value of the contract is R696 139 850,00. The exact GPS Coordinates are 25°44'44.8"S 28°11'46.0"E
Upgrading of Drommedaris Street, Phase 1, in Paarl, Western Cape. CIDB 7CE. The approximate GPS location has been placed along the proposed area of construction 33°41'37.9"S 18°59'01.6"E
Refurbishment for the 36 Hans Strijdom Building located on Erf 155345, 36 Hans Strijdom Avenue, Cape Town City Centre, Cape Town, Western Cape. The scope of works involve construction of a new façade, relocate the parking entrance, install new lifts, new services to offices, demolish internal offices
Resurfacing of roadways on Salt River Precinct situated in Salt River, Cape Town, Western Cape. CIDB 7CE. Scope of works could include: The works for the site clearance, earthworks and layer works include the following: Clearing of site. Demolition of concrete aprons, walls and channels. Bulk excavation
Construction of a mega-bridge called Msikaba Bridge with the main span of 580m supported from a pair of 127m-tall pylons. The deck will be 194m meters above the valley floor, located within Lusikisiki in the Eastern Cape as part of the N2 Wild Coast Toll Road. The total contract amount is approximately
Upgrades, additions and routine road maintenance of National Route N2 Section 8 at km 80.08 and Section 10 at km 73.50 and National Route R62 Section 6 at km 36.76 to Section 8 at km 33.55, Garden Route and Sarah Baartman District Municipalities, Western Cape & Eastern Cape. The GPS Marker has been placed