Construction of the Mandlakazi Upstream Bulk Section 1C in Mkuze, Zululand, KwaZulu-Natal. The contract value is R420 581 000. The scope of work comprises the construction of 8 500m of 1 000mm diameter GRP pipe with associated valves chambers and fittings and access roads. The GPS coordinate are 27°35'43.85"S,
Construction of the reticulation and distribution pipelines of Zone 1A of KwaHlokohloko SSA1 reticulation located primarily within Ward 10 in the Umlalazi Local Municipality approximately 5-7km from Eshowe along and on the left side of R66 towards Melmoth in Kwazulu-Natal. Value: R71 765 813.97. The
Construction of a 12ML/day water treatment works in Ga-Malekana, Limpopo. Estimated value of R 144 617 651.24. This project is part of the upgrading of the Dehoop/ Malekane Treatment Works. The scope of works could include: clearing of 2,6ha, new offices for Department Agriculture on adjacent property,
Rehabilitation of an 560mm potable water pipeline, valves, fittings and manholes in the Phalaborwa water supply scheme located in Mopani District, Limpopo. CIDB 8CE/ME. The project entails civil, structural and mechanical works relating to the rehabilitation of an existing pipeline within the existing
Construction of Mampuru bulk water scheme, Phase 1B which relates to the pump station, Sekhukhune District Municipality, Groblersdal, Limpopo. Project Value: R24 777 279.00. Pumpstation Implementation entails the construction of the following elements: Site clearance and excavation, pumpstation building,
Construction of the bulk water and retail water supply Phase 2 in Murangoni, Maranzhe, Vondo La Ntha, Vondo La Fhasi, Tshikunda and Matondoni (New names, Sengani, Makanga, Ramulongo and Mufungwani) in the Vhembe District Municipality, Limpopo. CIDB 8CE. The project is located in the Vondo cluster situated
Construction of reticulation and distribution pipelines for Zone 1C of the Kwahlokohloko SSA1 in Nkume, Gawozi and Eziqwaqweni Areas, Kwazulu-Natal Province. Value of R65 999 868.96. The project is located primarily in Ward 10 in the Mlalazi Local Municipality. The supply area is approximately 5-8km
Construction of Moutse and West water reticulation Phase 2, Contract 2C, Phucukane, Greater Sekhukhune District Municipality, Limpopo. Project Value: R40 426 354,00 The works entails the excavation, supply, bedding, laying, back filling and testing of the water pipelines for the internal reticulation
Construction of a desalination plant with a capacity of 20 million cubic metres per year in the Erongo Region, Namibia. The GPS coordinates are unknown and the marker has been placed at the Ministry of Agriculture, Water & Forestry Offices in Windhoek -22.5534031, 17.08506115.