You are currently logged out and we are unable to show you directory results. Please Log in or Subscribe for ALL the information relating to your search.

Found 2473 items with Total of 2674 results

Advertising



Projects

Malamulele South Villages WSS, Phase 1
117
  • 36322
Construction of phase 1, pumping system for Jimmy Jones, Mphambo Extentions, Xigamani and Muswani Villages, Limpopo. CIDB 8CE. The detailed scope of work is as follows: Power supply to abstraction works, Power supply to new high lift pumpstation and small power and lighting installation. The following


Projects

Robertville Water Tower & Pump Station
360
  • 23538
Construction of the Robertville 2.25Ml water tower and pump station, in Robertville, Randburg, Gauteng. CIDB 8CE. The work is broadly described, but not limited to: 2.25Ml concrete water tower, with associated piping, valve room at new tower site, guard and telemetry buildings, scour/overflow structures,


Projects

Kempsdale Dam Wall
163
  • 28951
Raising of the Kempsdale Dam wall and upgrading of the pump station on Portions 10 of Farm Bad Fontein No. 241 and Zon-Fontein No 257, the dam is located upstream of Kokstad Town within the Greater Kokstad Local Municipality, Harry Gwala District, Kwazulu-Natal. The project value is R160 306 471.25.


Projects

Laaispruit Dam Wall
134
  • 35730
Reconstruction of the Laaispruit dam wall in Marquard/Moemaneng, Free State. CIDB 7CE. Estimated GPS coordinates -28.672075829435553, 27.42133288540559.


Projects

Pegasus Canal Upgrade
127
  • 36522
Upgrading of Pegasus Canal in Equestria, Gauteng. CIDB 7CE. The works are located in the eastern part of the City of Tshwane under Region 6. The canal is a major stormwater system that drains areas between the Bronberg mountain, parts of Die Wilgers and Equestria. The GPS coordinates are unknown and


Projects

Hammarsdale High Level Reservoir Inlet Phase 2
114
  • 36725
Construction of a steel inlet main for phase 2 of the Hammarsdale High Level Reservoir going through Wards 04 & 103 in Hammarsdale, KwaZulu-Natal. CIDB 7CE. The scope of work could include the construction of approximately 2700m long, 500mm ᴓ steel inlet main. The 500mm Ø pipeline route starts at the


Projects

Coega SEZ, Phase 1
112
  • 36723
Construction of a bulk sewer connection line into the Coega SEZ Phase 1 in Gqeberha, Eastern Cape. CIDB 7CE. The scope of works includes the construction of approximately 4km of 1000mm diameter PVC-O gravity main from the existing connection point at the SEZ boundary, reinforced concrete chambers for


Projects

Riemvasmaak Informal Settlement
141
  • 35716
In-situ upgrading of the Riemvasmaak informal settlement, phase 1 in Caledon, Western Cape. Contract value of R29 277 969,00. Scope of works for this contract: Roads, stormwater reticulation, water reticulation, sewer reticulation, bulk earthworks and related retaining structures. The approximate GPS


Projects

Forest Hill Tower & Pumpstation Upgrade
154
  • 36425
Construction works for the water upgrades earmarked for the Foresthill tower and pumpstation located on Erf 68, Turffontein, 418 Rifle Range Road, Turffontein, Johannesburg, Gauteng. CIDB 8CE. Scope of works is to enhance the storage capacity of the existing water works at Foresthill in Johannesburg


Projects

Huntington WR
137
  • 35949
Construction of water reticulation in Huntington located in the Bushbuckridge municipality, Mpumalanga. CIDB 7CE. The GPS coordinates are not known and have been placed at the municipality offices 24°50'24.4"S 31°03'60.0"E

Advertising

Send me a Sample Based on these search results