The Republic of Mozambique has received nancing from the World Bank (WB) toward thecost of the Temane Reginal Transmission Project (TREP), and intends to apply part of the proceeds toward payments underthe Contract[1] for: Plant, Design, Supply & Installation, Testing and Commissioning of 400 kV AIS Substationns theor Temane Transmission Project (TTP), Lot 1 Plant, Design, Supply & Installation,Testing and Commissioning of a n ew 400/110 kV AIS Substation in Vilanculos, to be equipped with a 400 kV doublebusbar, and 110 kV double busbar system, byproviding all necessary HV, MV and LV equipment including protection, metering, SCMS,SCADA, telecommunication, auxiliaries and allsteel structures, foundations, cable ducts and all other associated works as perrequirements to complete. Civil works include foun dations for one 100 MVAr line reactor (three single phase units), one 100 MVArbus reactor (three single phase units) and 400/110 kV , 3 x single phase 50 MVA power transformers (four foundations including afourth foundation for a spare transformer unit to be cons tructed by the Contractor). Plant, Design, Supply& Installation, Testing and Commissioning of a new 400/275 kV AIS Substation in Chibuto, to be equipped with a400 kV double busbar, and a 110 kV double busbar system, by pro viding all necessary HV, MV and LV equipment including foundations, cable ducts and all other associatedworks as per requirements to complete. Civil works include foundati ons for two 100 MVAr line reactor (2 x 3 x single phase units),one 100 MVAr bus reactor (3 x single phase units) and 400/275 kV, 3 x single phase 50 MVA power transformer foundations (fourfoundations including a fourth foundation for a spare transformer unit to be constructed by theContractor). Plant, Design, Supply & Installation, Testing and Commissioning of a new 400/66 kV AISSubstation in Matalane, to be equipped with a 400 kV double busbar, 2 x 400 kV line bays, 1 x 400 kV t ransformer bay, byproviding all necessary HV, MV and LV equipment including protection, metering, SCMS, SCADA and telecommunicationand all steelstructures, foundations, cable ducts and all other associated works as per requirements to complete. Civil works incl udefoundations for 400/66 kV, 4 x single phase 133,33 MVA power transformers. Plant, Design, Supply & Installation, Testing and Commissioning of a new 400 kV AIS Substation extension at Maputo Substation, to be equippedwith a 400 kV double busbar and transfer bus bar extension, 400 kV bus coupler bay, one 400 kV line bay to Matalane, by providing alll winecessary HV equipment including protection, metering, SCMS, SCADA and telecommunication and all steel structures,foundations, cable ducts, fencing and all other associated works as per requirements to complete. Civil works include earthworks forlling up of th e extension area and levelling with the existing substation area. All substations must be completedwithin 24 months f rom the Commencement Date. Training of Employer's personnel, supply of mandatory and recommended spare material and equipment, for substation equipment. Reactors for Vilanculos and Chibutosubstations and power transformer s for Vilanculos, Chibuto and Matalane substations will be designed, supplied and installed undera separate Lot (all as 3 x single phase units) Statcoms/SVC’s located within the Vilanculos and Chibutosubstations) shall be designed, supplied and installed under a separate Lot.