About this development
Upgrades to the existing manufacturing campus situated at 2 Shosholoza Avenue, Dunnottar, Nigel, Gauteng. Package 2 would increase the manufacturing capability from three / four to six trains per month. The scope of works includes: (1) Construction of a new MO5B testing facility / building. M05B will house two testing bays for Gibela’s test and commissioning department as well as amendments to existing services due to clashes. (2) MO2C Enclosure: enclosing 1700m² of Package 1 as well as additional infrastructure. GPS Co-Ordinates Lat -26.3540705, Long 28.4600167. Value R34 Million
Project at a glance
Gibela Plant Package 2 is located in Nigel. The project is classified in the Private sector. Its current recorded stage is Complete. The recorded project value is R 31 Million - R 60 Million.