Construction of Coffee Bay Regional water supply scheme - Phase 3B Part A, located in Coffee Bay, Eastern Cape. Estimated value of R34 542 670,00. The scope of work includes: Construction of 36km of village reticulation; construction of 2 No. 400kl reinforced concrete reservoirs; construction of 113 No. of standpipes; construction of break pressure tanks; testing, cleaning and disinfection of pipelines and reservoirs; tie-in into, testing and commissioning of pipes laid by others and where required repair leaks on pipes constructed by others and incorporate into the new scheme. The exact co-ordinates are currently not available so the marker has been placed in Coffee Bay at 31°55’8.93”S, 29°1’54.93”E.
Project at a glance
Coffee Bay RWSS - Phase 3B is located in Coffee Bay. The project is classified in the Public sector. Its current recorded stage is Complete. The recorded project value is R 31 Million - R 60 Million.