Project overview
About this development
Construction of the Coffee Bay Regional Water Supply, Phase 3C, in Coffee Bay, Eastern Cape. Project value of R102 406 955.43. Scope of work: Construction of 9km gravity main water pipes; 72km of village reticulation; two 500kl and one 250kl reinforced concrete reservoirs; 127 standpipes; break pressure tanks; tie-in into, testing and commissioning of 8km pipes laid by others and where required, repair leaks and incorporate into the new scheme; testing, cleaning and disinfection of reservoirs. The exact co-ordinates are currently not available so the marker has been placed in Coffee Bay at 31°55’8.93”S, 29°1’54.93”E
Project at a glance
Coffee Bay RWS, Phase 3C is located in Coffee Bay. The project is classified in the Public sector. Its current recorded stage is L2B Shelved. The recorded project value is R 61 Million - R 200 Million.