Project overview
About this development
Construction of a bulk water connection line into the Coega SEZ Phase 1 in Gqeberha, Eastern Cape. The project value is R56 560 227,13. The scope of works includes the construction of approximately 4km of 1000mm diameter PVC-O gravity main from the existing connection point at the SEZ boundary, reinforced concrete chambers for the gravity mains. The GPS marker has been placed at the proposed site 33°43'37.3"S 25°38'43.1"E.
Project at a glance
Coega SEZ, Phase 1 is located in Gqeberha (Port Elizabeth). The project is classified in the Public sector. Its current recorded stage is Awarded. The recorded project value is R 31 Million - R 60 Million.