Project overview
About this development
Construction of infrastructure works under cluster 2 water backlog project in the villages of Tsakana, Gcina, Manuneni, Guse, Qungu, Dlomo, Nyongwana, Khalane, Dayimane at Intsika Yethu Local Municipality area, Eastern Cape. The scope of work will be the construction of the following: Bulk pipelines (14km pumping mains), 12km mPVC pipeline, 2km steel pipeline, gravity mains (32km pipeline), 4km mPVC pipeline, 28km HDPE pipeline, 71 communal standpipes, ancillary work (valves and chambers), 1ML reinforced concrete reservoirs and 2 x 150kl pressed steel tank. The exact co-ordinates are currently not available however the approximate area of location is 31°55'53.4"S 27°38'36.5"E.
Project at a glance
Cluster 2 Water Backlog Project (RS5 Phase 3) is located in Eastern Cape (047). The project is classified in the Public sector. Its current recorded stage is Complete. The recorded project value is R 61 Million - R 200 Million.