Project overview
About this development
Construction of the 560km long high voltage 400kv electricity transmission line from Temane, in Inhambane, to Maputo in Mozambique. Estimated cost: US$ $550 million. The project will include: Double circuit, 400kV transmission line, approximately 25 km long, between Temane and Vilanculos; A single circuit,400kV transmission line, approximately 560km long, between Vilanculos and Maputo; A new 400/110kV Substation at Vilanculos; New 400k400/275kV substation at Chibuto, New 400/275kV substation at Matalane; Extension to the existing 400/275kVsubstation at uto and associated works (control, protection, communication, etc). The exact co-ordinates are currently not available however the approximate area of location is lat: -21.7506284; long: 35.06242299999999
Project at a glance
Temane - Maputo Power Line, Mozambique is located in Mozambique. The project is classified in the Public Private Partnership sector. Its current recorded stage is Complete. The recorded project value is R 200 Million+.