Project overview
About this development
Construction of the Setlopo water supply, Phase 1 in Setlopo, Ngaka Modiri Molema District Municipality, North West. Project value R79 951 567,17 . Scope of works could include: Laying of bulk line of PVC-U from boreholes to storage consisting of uPVC pipes, pipe diameter 75mm to 160mm, total length of about 21,5km. Equipping and electrifying of fifteen new boreholes. Erecting a 559kl elevated steel tank on a 15m stand in Ward 22. Erect a 406kl elevated steel tank on a 15m stand in Ward 31, erecting a 1 580kl elevated steel tank on a 15m stand in Ward 35 inclusive of the standard operating procedure (SOP) for the scheme. GPS coordinates of the site meeting are 25°55'58.0"S 25°39'22.0"E
Project at a glance
Setlopo WS, Phase 1 is located in Mahikeng (Mafikeng). The project is classified in the Public sector. Its current recorded stage is Underway. The recorded project value is R 61 Million - R 200 Million.