About this development
Construction of services and infrastructure for the RRT (Rustenburg Rapid Transport) Project which will be known as "Ya Rona". The RRT project’s main routes will make use of 100 articulated buses. The system will also include direct and feeder-and-distribution bus systems that will link with the RRT trunk roads running along the R510 and R565 roads into the city centre. Located in Rustenburg, North West. The estimated project costs are R 3-billion.
Project at a glance
RRT (Rustenburg Rapid Transport) Project is located in Rustenburg. The project is classified in the Public sector. Its current recorded stage is Complete. The recorded project value is R 200 Million+.