Rehabilitation works of Tiga Dam Phase II in Kano, Nigeria. Project cost is estimated at N11.83 billion. Scope of works could include: Restoration of the downstream slope embankment to 1:2.5 by stepped fill and compaction of the degraded downstream curvilinear section to return the dam back to its original design vertical and horizontal geometries as required. The compaction degree shall not be less than 98% at Chainage 0+000 to 3+ 400. Laying of asphalt pavement on the entire dam embankment crest. GPS coordinates 11.4139341, 8.409685699999999.
Project at a glance
Rehabilitation Works of Tiga Dam Phase II is located in Nigeria. The project is classified in the Public sector. Its current recorded stage is Complete. The recorded project value is R 200 Million+.