Project overview
About this development
Construction of a proposed photovoltaic (PV) plant on the remaining extent of portion 24 of the farm Spruitfontein 341 which is situated next to Marikana Platinum Mine in Buffelspoort in North West Province. The project includes the installation of 11 inverters and 29 808 photovoltaic solar modules, with a step up transformer to connect to the 88kV substation. The farm will produce 244 643 MWh of energy over the 20 year contract period. RustMo1 is destined to supply power to the Eskom grid upon commencement of commercial operation, scheduled for November 2013.
Project at a glance
Photovoltaic Plant, North West is located in North West. The project is classified in the Private sector. Its current recorded stage is Complete. The recorded project value is R 31 Million - R 60 Million.