Project overview
About this development
Construction and commissioning of the Ludeke Dam and ancillary works. The Ludeke Dam will have a storage capacity of 14.5 million m3 and consists of a 240m long, 40m high rockfill main embankment and a 280m long, 15m high saddle embankment. Both the main and saddle embankments include a central clay core and a sand filter system The side channel spillway arrangement comprises a 60m long concrete ogee section that discharges into a 220m long concrete lined chute. The outlet works to the Ludeke Dam comprises a 40m high reinforced concrete wet well intake tower with multiple level sluice-gate offtakes that discharge through a 750mm diameter steel outlet pipe and a 1 200mm diameter steel scour pipe.Located in Bizana, Eastern Cape Province. CIDB 9: R130 Million Plus.
Project at a glance
Ludeke Dam is located in Mbizana. The project is classified in the Public sector. Its current recorded stage is Complete. The recorded project value is R 200 Million+.