Project overview
About this development
Construction of a 360 000-ton/annum ferrochrome smelter in Steelpoort, Limpopo. Phase 1 of the Lion ferrochrome project was commissioned in September 2006. The Xstrata project team is now conducting an economic study and budget for the 360 000-t/y phase 2 expansion of the ferro-chrome operation. The phase 2 expansion is expected to be a carbon copy of the first phase. The development will entail a total capital investment of R4.9 billion and includes R700 million for the concurrent development of the Magareng mine.
Project at a glance
Lion ferrochrome complex expansion phase 2, Limpopo is located in Limpopo. The project is classified in the Private sector. Its current recorded stage is Complete. The recorded project value is R 200 Million+.