Project overview
About this development
Construction of four separate rising mains varying in size from 200mm to 315mm and uPVC class 9 and 12 pipes, with a total length of approximately 8.4km. Mechanical and electrical works will be performed under a separate contract. The pipes will be installed within an urban environment and within close proximity to other infrastructure and homes. Fort Beaufort Bulk Water Supply: Newtown, Hillside, Bhofolo and Town Reservoir Pipelines and Pump House Structures (Contract 3) in Fort Beaufort, Eastern Cape Province. The exact GPS Co-ordinates are : 32°46'44.1"S 26°37'11.6"E
Project at a glance
Fort Beaufort Bulk Water Supply: Contract 3 is located in KwaMaqoma (Fort Beaufort). The project is classified in the Public sector. Its current recorded stage is Complete. The recorded project value is R 31 Million - R 60 Million.