Rush to spend infrastructure millions in Uitenhage



21-06-2019
Read : 144 times
Bizcommunity.com
Source

In March the Treasury gave Nelson Mandela Bay Metropolitan Municipality R200m for the eradication of the bucket system, electrification of shacks, and fixing of roads and infrastructure. The money has to be spent by the end of June, according to the ward councillor for KwaNobuhle, Uitenhage. But the municipality has had difficulty spending the money due to protest action.

Ward 47 Councillor Nonthuthuzelo Skweyiya (ANC) said the tarring of potholed Mabandla Road in KwaNobuhle was put on hold after owners of small businesses demanded a 30% share of the money that would be spent on paving Sivo Road. The angry business owners closed down Skweyiya’s offices in May and again on Wednesday this week.

But while tarring potholed Mabandla Road was delayed by the protests, “the project to pave Sivo Street is still ongoing, because residents who live in potholed streets have vowed they are not going to allow it to stop”, said Skweyiya.

This week, Ndlambe Street was tarred and its many smaller potholes fixed. Residents have been complaining about potholes in Ndlambe Street for three years. Even though it is the main route for taxis driving to Extension 1 (Angola) from town, motorists tend to avoid Ndlambe Street, because it has a giant, flooded pothole.

Reverend Raymond Punana, of the Christian Assemblies Church, said, “There is always mud around our church because of this leaking underground water. We reported it several times and have now given up … It’s been years.”

The water which seeps out of the ground between Shiwo and Ndlambe Streets erodes the road, steadily enlarging the pothole.

In April, Ward 46 Councillor Lindelwa Qukubana (ANC) told GroundUp that, “the giant pothole was fixed three times, but there is a re-occurence because of the oozing water that is peeling the tar at Ndlambe Street”.

On Wednesday, Qukubana explained that “the pothole was skipped [during the recent tarring] so that it can be fixed this week properly. The contractor wants to make sure it is permanently fixed… once and for all … We’ve got to spent the R200m by end of this month”.

Sign up for Free Daily Building and Construction News