On the road to completion

PPA8932


30-10-2018
Read : 187 times
The Witness
Source

Preparation of final span for casting of deck slab on the Umhlathuze Bridge. Upgrading of 35 km of the N2 between Mtunzini toll plaza and Empangeni interchange on the North Coast, which started three years ago, is on track for completion at the end of June 2019, a statement said. The South African National Roads Agency is building a new north-bound carriageway, with the existing road to become the future south-bound carriageway. The R946-million project is one of the biggest road developments being undertaken by Sanral in KwaZulu-Natal.